PV feed-in tariff Schaffhausen 2026

The PV feed-in tariff in Schaffhausen follows the Swiss Federal Office of Energy (SFOE) quarterly reference market price in the SH POWER grid area in 2026; systems up to 30 kW receive a minimum of 6.00 Rp./kWh. For SH POWER, 10.27 Rp./kWh for the first quarter and 3.90 Rp./kWh for the second quarter have been published, both excluding VAT. The third-quarter value will only be published on 14 October 2026 at 12:00 and must not be anticipated. A different grid operator, a system above 30 kW or a medium-voltage connection requires further clarification. Guarantees of origin are remunerated separately and handled through an SH POWER agreement from 4 kW, while the Pronovo one-time incentive is a separate funding route.

How high is the PV feed-in tariff in Schaffhausen in 2026?

In the SH POWER grid area, exported solar electricity in 2026 is valued at the quarterly SFOE reference market price; SH POWER also states a 6.00 Rp./kWh minimum up to 30 kW. The published values are 10.27 Rp./kWh for Q1 and 3.90 Rp./kWh for Q2. The grid area, output, self-consumption, guarantees of origin and Pronovo RU must be calculated separately.

Important

As of 27 August 2026, SH POWER’s Q3 2026 value has not yet been published; the SFOE lists 14 October 2026 at 12:00 for publication. The 6.00 Rp./kWh minimum also applies to the output class up to 30 kW named in the tariff schedule, not automatically to every system in Canton Schaffhausen. SH POWER phrases the 4 kW guarantees-of-origin threshold in two ways: automatic settlement up to 4 kW, but an agreement from 4 kW. Confirm the treatment of exactly 4 kW in writing.

Key figures: PV feed-in tariff Schaffhausen

Key figures for PV feed-in tariff Schaffhausen, updated 27 August 2026
MetricValue
Minimum up to 30 kW6.00 Rp./kWh according to SH POWER
Published quarterly values in 2026Q1: 10.27 Rp./kWh; Q2: 3.90 Rp./kWh
Guarantees of origin2.50 Rp./kWh; separate agreement from 4 kW
SFOE Q3 2026 publication14 October 2026 at 12:00
Larger systems with self-consumption30 to 150 kW: 180 divided by system output in kW

What determines the right path.

The grid area is the first decision point. The published tariff schedule belongs to SH POWER and applies to feed-in to its grid; Canton Schaffhausen alone does not determine the feed-in tariff. Before quoting, assign the address to the responsible distribution-grid operator.

Since 1 January 2026, the quarterly reference market price under Art. 15 para. 1 EnG replaces a flat annual value where the producer and grid operator do not agree on remuneration. The SFOE publishes the price by 12:00 on the 10th working day after each quarter; Q3 2026 follows on 14 October 2026.

Installed PV output is the decisive quantity. SH POWER states a 6.00 Rp./kWh minimum up to 30 kW; for systems from 30 to 150 kW with self-consumption, the tariff schedule reduces the output-dependent minimum under the formula 180 divided by system output in kW, for example to 3.00 Rp./kWh at 60 kW.

Self-consumption changes the quantity, not automatically the tariff. A heat pump, wallbox, battery or ZEV reduces the surplus that is remunerated at all. For the remaining feed-in, SH POWER’s published SFOE values of 10.27 Rp./kWh for Q1 and 3.90 Rp./kWh for Q2 2026 are the concrete comparison points.

Guarantees of origin are a separate revenue stream. SH POWER states 2.50 Rp./kWh for guarantees of origin; for systems from 0 to 4 kW this amount is settled automatically with the feed-in tariff, while from 4 kW a separate purchase agreement, certification and registration in the Pronovo system are required.

Timing and the tax basis belong in the revenue calculation. SH POWER’s 2026 tariff schedule states feed-in and guarantees-of-origin remuneration generally excluding VAT; switching to HKN remuneration must be notified two months before the quarter starts and the Pronovo standing order confirmed no later than 14 days before the change.

How the project stays cleanly managed.

  1. 1

    Establish the grid area and metering pointrecord the address, grid connection point and responsible distribution-grid operator in the project file. The following tariff schedule is relevant only where SH POWER purchases the electricity; elsewhere, use the other operator’s current feed-in rules.

  2. 2

    Classify the systemcalculate installed DC output, voltage level, expected annual generation and self-consumption share. Up to 30 kW, the 6.00 Rp. minimum applies; from 30 to 150 kW with self-consumption, also check the formula 180 divided by system output, while above 150 kW the tariff schedule states a 0.00 Rp./kWh minimum.

  3. 3

    Prepare metering and registrationalign the technical data, connection request, metering concept and actual installed output with SH POWER. A medium-voltage connection or output outside the published standard classes should only be included in the quote after written clarification with the grid operator.

  4. 4

    Model self-consumptioncompare the load profile, heat pump, wallbox, battery and any ZEV or LEG structure with PV generation. Only the remaining surplus is valued at the relevant quarterly rate; the SFOE publication is exclusive of VAT and is not a fixed annual price.

  5. 5

    Calculate feed-in, guarantees of origin and funding separatelySH POWER lists 2.50 Rp./kWh for guarantees of origin, while Pronovo handles the one-time incentive as federal funding. The economic calculation should show at least self-consumption value, feed-in, guarantees of origin and Pronovo RU as separate lines.

  6. 6

    Trigger the guarantees-of-origin agreement and deadlines only where needed: for systems from 4 kW, certify the system data, register the system in Pronovo’s guarantees-of-origin system and request the SH POWER change two months before the quarter starts. The producer must confirm the Pronovo standing order no later than 14 days before the change.

Questions to settle before the quote.

  • Confirm the SH POWER grid area, installed DC output and responsible grid operator before requesting a quote
  • Classify the 10.27 Rp./kWh first-quarter and 3.90 Rp./kWh second-quarter 2026 values correctly
  • Check the 6.00 Rp./kWh minimum up to 30 kW and the 180-per-kW formula for larger systems with self-consumption
  • Prepare guarantees of origin separately with 2.50 Rp./kWh, Pronovo certification, the 4 kW threshold and the two-month deadline

More questions: PV feed-in tariff Schaffhausen

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Schaffhausen, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

Solar installation in Schaffhausen – cleanly coordinated

What matters here is which grid operator is responsible: in the city of Schaffhausen it is SH POWER, in the rest of the canton EKS AG. Funding runs via the federal one-time payment (KLEIV up to 100 kW, GREIV from 100 kW) through Pronovo, complemented by the cantonal energy programme, whose applications must be submitted via the energy portal before construction starts.

Guide

Assessing PV economics in Canton Zug correctly

Assess which factors genuinely drive PV system economics in Canton Zug, from self-consumption and current WWZ tariffs to ZEV models, LEG and Pronovo one-time payment.

Regional service

PV Installation Schaffhausen – Roof & Electrical

Canton Schaffhausen benefits from approximately 1,700 sunshine hours per year thanks to the Rhine valley climate. SH POWER compensates on a market basis with quarterly billing (range 5.45–12.22 Rp./kWh depending on system size and commissioning date). The compact canton enables particularly short approval timelines. The smart meter rollout (80% by 2027) creates infrastructure for dynamic tariffs and precise self-consumption metering.

Guide

Self-consumption, vZEV and LEG in Schaffhausen: using solar power correctly

Assess when self-consumption, vZEV or LEG make sense in Schaffhausen: check metering model, grid connection, storage, tenant electricity and Pronovo separately.

Service

Solar system installation

From the initial estimate and 3D survey through a transparent quote to full commissioning — one project, one process, one contact.

Guide

vZEV and local electricity communities: planning PV self-consumption in Schaffhausen

Assess when ZEV, virtual ZEV or local electricity community makes sense for PV in Schaffhausen: prepare metering concept, grid operator, participants, storage and billing cleanly.