Skip to content
GuideProject flowSchaffhausen

PV grid connection Schaffhausen: EKS workflow 2026

The PV grid connection in Schaffhausen is not a single form in the standard case, but a workflow through the EKS portal, electrical contractor, meter, safety certificate and commissioning. In the EKS installer portal, specialist contractors can register and manage generation systems, devices, batteries, completion notices and change notifications. One important exception concerns plug-in solar devices up to 600 watts: after installation, they too must be registered with EKS using the form and the manufacturer’s declaration of conformity. For fixed PV systems, it also matters whether guarantees of origin are to be transferred to EKS; EKS only remunerates guarantees of origin for systems up to and including 500 kWp if the system is certified by Pronovo and registered in the guarantee-of-origin system. The building-law notification to the municipal building authority remains separate and must be submitted in Canton Schaffhausen no later than 30 days before construction starts.

What you need to know first.

For the grid connection of a PV system in Schaffhausen, grid operator, EKS portal, meter process, safety certificate and Pronovo/HKN must fit together before commissioning. Plug-in systems up to 600 watts also require notification; fixed systems need professional electrical coordination and, separately, the building-law 30-day notification to the municipality.

Important

As of 2026, the key boundary is this: a municipal 30-day notification in Canton Schaffhausen does not automatically make the system grid-ready. EKS portal, meter, safety certificate, independent inspection, Pronovo certification and guarantee-of-origin standing order are separate technical or energy-market steps.

What determines the right path.

The first factor is the responsible grid operator at the connection point: EKS operates an installer portal in Canton Schaffhausen where consumption systems, generation systems, devices, batteries, completion notices and change notifications are managed. Without this assignment, portal, meter process and feed-in contract cannot be planned reliably.

The second factor is electrical documentation: according to ESTI, the safety certificate confirms that an electrical installation meets the requirements of Art. 3 and 4 NIV at the time of issue. For photovoltaic systems, ESTI requires the photovoltaic measurement and test protocol under Directive 233.

The third factor is the acceptance inspection: for non-plan-approval PV systems connected to a low-voltage distribution grid, ESTI states that the owner must arrange an acceptance inspection by an independent inspection body within six months and submit the safety certificate to the grid operator.

The fourth factor is the meter: for plug-in solar devices, EKS explicitly states that a digital electricity meter with backstop is required and that EKS installs a smart meter if needed. For fixed systems, the meter question therefore belongs in commissioning planning, not at the end of the project.

The fifth factor is guarantee-of-origin remuneration: EKS remunerates guarantees of origin in addition to the feed-in tariff only if the system produces solar power, has a capacity up to and including 500 kWp, is certified by Pronovo, is registered in the guarantee-of-origin system, is permanently connected to the EKS grid and has a valid feed-in contract plus guarantee-of-origin standing order.

The sixth factor is the separation between grid and building law: the cantonal notification form requires the solar system to be submitted to the local building authority no later than 30 days before construction starts. This notification does not replace the EKS portal, safety certificate, meter change or Pronovo/HKN steps.

How the project stays cleanly managed.

  1. 1

    Determine grid area and project sizebefore the quote, clarify whether EKS is responsible at the connection point, whether a battery is included and whether the system can fall within the guarantee-of-origin framework up to and including 500 kWp. These details steer portal, feed-in and metering concept.

  2. 2

    Start building-law handling in parallelsubmit Canton Schaffhausen’s solar notification form to the local building authority no later than 30 days before construction starts. If the project deviates from Art. 32a RPV, involves protected buildings or conflicts with design requirements, a building permit may be needed.

  3. 3

    Prepare the EKS portal through the specialist contractorthe registered electrical or solar contractor creates the generation system, devices and any battery in the installer portal. EKS notes that processing of a grid-connection request only starts after the customer login has been confirmed.

  4. 4

    Define meter and metering conceptbefore installation, clarify whether an existing meter must be replaced and whether feed-in, self-consumption, battery or later vZEV/LEG use must be measured cleanly. EKS explicitly names the digital meter with backstop as a requirement for plug-in systems.

  5. 5

    Sequence safety certificate and inspectionafter installation and final inspection, have the safety certificate with photovoltaic measurement and test protocol prepared. For non-plan-approval PV systems on the low-voltage grid, ESTI requires the independent acceptance inspection to be arranged within six months.

  6. 6

    Complete commissioning and feed-infinish completion notice, meter release and feed-in contract cleanly before regular operation. Anyone who wants to transfer guarantees of origin to EKS must, according to EKS, bring together Pronovo certification, the guarantee-of-origin standing order and the valid feed-in contract.

  7. 7

    Check Pronovo activationafter receiving the contract, EKS creates the guarantee-of-origin standing order with Pronovo; the operator must confirm the Pronovo email link. According to EKS, guarantees of origin can be settled retroactively no earlier than from the beginning of the current quarter.

Questions to settle before the quote.

  • Before the quote, clarify whether EKS is responsible at the connection point or another local grid operator
  • Prepare generation system, battery, completion notice and change notification in the EKS installer portal
  • Plan the safety certificate, PV measurement and test protocol and independent inspection under ESTI/NIV rules
  • Complete the guarantee-of-origin standing order, feed-in contract and Pronovo activation from the current quarter cleanly

Common questions on this topic.

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Schaffhausen, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

Solar installation in Schaffhausen – cleanly coordinated

What matters here is which grid operator is responsible: in the city of Schaffhausen it is SH POWER, in the rest of the canton EKS AG. Funding runs via the federal one-time payment (KLEIV up to 100 kW, GREIV from 100 kW) through Pronovo, complemented by the cantonal energy programme, whose applications must be submitted via the energy portal before construction starts.

Guide

Grid Operator Registration PV Bern: BKW & ewb Process

In canton Bern the responsible grid operator depends on the location: ewb in the city of Bern, BKW across most of the rest of the canton, plus local utilities such as Localnet (Burgdorf). The contractor submits a technical connection application (TAG) before construction; building is only permitted after approval.

Regional service

PV Installation Schaffhausen – Roof & Electrical

Canton Schaffhausen benefits from approximately 1,700 sunshine hours per year thanks to the Rhine valley climate. SH POWER compensates on a market basis with quarterly billing (range 5.45–12.22 Rp./kWh depending on system size and commissioning date). The compact canton enables particularly short approval timelines. The smart meter rollout (80% by 2027) creates infrastructure for dynamic tariffs and precise self-consumption metering.

Guide

What to consider for a PV system? The Swiss guide before your first quote

The key points before buying a photovoltaic system – roof, electricity use, system size, components, costs, incentives and permits – in the order that actually matters.

Service

Solar system installation

From the initial estimate and 3D survey through a transparent quote to full commissioning — one project, one process, one contact.

Guide

Basel-Stadt solar offensive: what owners should clarify before PV planning

Understand what Basel-Stadt’s solar offensive means for owners: suitable roof areas, protected buildings, notification path, incentives, IWB connection and project timing.