Short answer
Can I combine the winter-power contribution with the area-potential contribution?
Guidance for owners in Graubünden who want to know before requesting a quote which of the two cantonal PV funding programmes their roof qualifies for, and in which order application, confirmation and construction start must happen.
Important
Confirmed contributions are maximum amounts per application. If the completed system deviates from the project submission underlying the funding decision, contributions may be reduced, cancelled or reclaimed under Art. 29 BEG. The confirmation is valid for three years from the date of the decision and can be extended by at most two years on written request. This page provides technical orientation and replaces neither advice from the Office for Energy and Transport nor tax advice.
At a glance
Key figures: PV funding Graubünden
| Metric | Value |
|---|---|
| Winter power (Art. 23a BEG) | CHF 300/kWp, min. CHF 900, max. CHF 200,000 |
| Area potential (Art. 23b BEG) | CHF 150/kWp, min. CHF 450, max. CHF 50,000 |
| Tilt for winter power | 60° to 90°, orientation E–S–W (90°–180°–270°) |
| Minimum system size | 3 kWp |
| Site requirement | Global radiation > 1250 kWh/m² per year |
| Application | Before construction, online at energie.gr.ch plus paper form |
| Validity of confirmation | 3 years, extendable by max. 2 years |
Decision points
What determines the right path.
Tilt and orientation determine the programme: the winter-power contribution requires a 60 to 90 degree tilt and east–south–west orientation, while the area-potential programme allows northeast to northwest (45°–180°–315°).
For the area-potential programme the energy reference area is decisive: the reference demand is 20 W/m², only capacity above 30 Wp/m² of energy reference area is funded, and only for predominantly residential use under building categories I and II of SIA standard 380/1.
Site quality must be documented: both programmes require global radiation above 1250 kWh/m² per year according to the cantonal potential map.
Shading rules out the winter-power contribution: the minimum distance of the panels from the ground is 0.5 per mille of the site altitude, and the panel may not be shaded more than 10 percent in January and February, based on 20 years of MeteoSwiss data.
The two cantonal contributions cannot be combined, and together with other public or national contributions they may not exceed 50 percent of the project expenditure under Art. 27 BEG.
Sequence
How the project stays cleanly managed.
- 1
Record roof, tilt, orientation and site altitude, and use the cantonal potential map to check whether global radiation exceeds 1250 kWh/m² per year.
- 2
Decide which programme applieswinter power under Art. 23a BEG for steep facade or roof designs, area potential under Art. 23b BEG for residential buildings with a clearly oversized system.
- 3
File the application online on the energie.gr.ch platform, then submit the duly signed application form on paper to the Office for Energy and Transport; only then is the application considered filed.
- 4
Wait for the contribution confirmation and only then begin implementation or purchases, unless an early construction start has been approved.
- 5
After completing the work, record the implementation on energie.gr.ch and submit the signed final form; payment follows once all documents have been reviewed.
Checklist
Questions to settle before the quote.
- Check the 60° to 90° tilt and east–south–west orientation required for the winter-power contribution
- Calculate the 20 W/m² reference demand and the 50 percent threshold for the area-potential programme
- Verify global radiation above 1250 kWh/m² per year using the cantonal potential map
- File the application before construction starts and respect the 50 percent cap alongside Pronovo funding
FAQ
More questions: PV funding Graubünden
Sources
Official sources & references.
The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.
- Guideline and conditions: photovoltaic systems for winter power (version 1/26)Office for Energy and Transport Graubünden
- Guideline and conditions: photovoltaic systems for using the area potentialOffice for Energy and Transport Graubünden
- Photovoltaic funding programme Canton GraubündenOffice for Energy and Transport Graubünden
- Energy Act of Canton Graubünden (BEG, BR 820.200)Canton Graubünden, collection of laws
- Energy Ordinance of Canton Graubünden (BEV, BR 820.210)Canton Graubünden, collection of laws
- One-time payment for photovoltaic systems (KLEIV, GREIV, HEIV)Pronovo AG