PV permits Graubünden: 15 working days notification

Graubünden regulates roof-mounted solar systems through a notification rather than a building application. Under Art. 40b para. 1 of the cantonal spatial planning ordinance (KRVO), roof-mounted solar systems are subject to the notification duty set out in Art. 40a KRVO. In practice this means the project must be reported in writing to the municipal building authority before implementation. The authority then has 15 working days to notify any building permit requirement by way of an appealable ruling, while also stating whether the project falls under the ordinary or simplified procedure and whether additional permits are required. If that notification does not arrive, Art. 40a para. 3 KRVO applies: without a response within 15 working days, the owner may start work. Whether a roof system is permit-free at all is decided by the municipal building authority under Art. 40b para. 2 KRVO on the basis of federal law, which sets the standard of sufficient integration. The municipal level is therefore decisive in practice: municipalities may specify that even insufficiently integrated systems are permit-free in aesthetically less sensitive zones such as commercial and industrial areas, and conversely they may provide in their building law that systems on buildings under a specific protection or conservation regime always require a permit.

Do I need a building application for a roof-mounted solar system in Graubünden?

Guidance for owners in Graubünden who want to know before installation whether a notification is sufficient, when the 15-working-day deadline starts running and which municipal special rules could derail their project.

Important

The 15-working-day period is not a permit but a silence deadline: it only means the municipality has not imposed a permit requirement. Substantive law, municipal design rules and further permits remain unaffected, and the building authority may still open a procedure ex officio if there are indications of a violation. Since Graubünden regulates much at municipal level, the information from your own municipality is decisive. This page provides technical orientation and replaces neither that information nor legal advice.

Key figures: PV permitting Graubünden

Key figures for PV permitting Graubünden, updated 02 August 2026
MetricValue
Procedure for roof systemsNotification duty instead of application (Art. 40b para. 1 KRVO)
Deadline15 working days from notification (Art. 40a KRVO)
If the municipality does not respondWork may begin (Art. 40a para. 3 KRVO)
ResponsibleMunicipal building authority
Permit-free facade areaup to 6.0 m² per facade inside, 2.0 m² outside building zones
Legal basisKRVO (BR 801.110), Art. 40, 40a, 40b

What determines the right path.

The municipality is the decisive body: under Art. 40b para. 2 KRVO the municipal building authority assesses on the basis of federal law whether the system is sufficiently integrated and therefore permit-free.

Protection and conservation rules can trigger a permit requirement: under Art. 40b para. 4 KRVO municipalities may provide in their building law that solar systems on protected buildings always require a permit.

Commercial and industrial zones can be simpler: under Art. 40b para. 3 KRVO municipalities may determine that even insufficiently integrated systems are permit-free in aesthetically less sensitive zones.

Facade systems follow their own threshold: low-reflection facade solar systems built to the state of the art are exempt from the permit requirement up to 6.0 m² of absorber area per facade inside building zones and up to 2.0 m² outside building zones (Art. 40 para. 1 no. 16 KRVO).

Permit-free does not mean rule-free: under Art. 40 para. 3 KRVO an exemption from the permit requirement releases neither from compliance with substantive law nor from obtaining other permits, and the building authority may open a permit procedure ex officio if there are indications of a violation.

How the project stays cleanly managed.

  1. 1

    Before planning, check the municipal building law and zoning rules for special provisions under Art. 40b paras. 3 and 4 KRVO for the zone or the building.

  2. 2

    Design the system so that the federal requirements on sufficient integration are met, since this is exactly what the municipality assesses.

  3. 3

    Notify the municipal building authority in writing before implementation begins (Art. 40a para. 1 KRVO).

  4. 4

    Wait out the 15 working daysif an appealable ruling arrives, follow the procedure it specifies; if none arrives, work may begin.

  5. 5

    In parallel, start the grid operator registration and the Pronovo application for the one-time payment, as these run independently of the building-law process.

Questions to settle before the quote.

  • Submit the written notification to the municipal building authority before work begins
  • Understand the 15-working-day deadline and what happens if the authority stays silent
  • Clarify municipal special rules for protected buildings and for commercial and industrial zones
  • Distinguish the permit-free facade areas of 6.0 m² inside and 2.0 m² outside building zones

More questions: PV permitting Graubünden

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Graubünden, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

PV Installation Graubünden – Roof & Electrical

Graubünden is the canton with Switzerland's greatest alpine solar potential. Thanks to altitude and cold, PV systems here deliver 30–50% higher yields than in the midlands. Repower compensates from 6 Rp./kWh + HKN bonus. The Muttsee dam wall (2,500 m) with 5,000 panels delivers 3.3 million kWh/year – with three times higher winter production than comparable lowland systems. Alpine installation requires specialised mounting structures for extreme wind and snow loads.

Guide

Solar Permit Bern: Notification Instead of Building Permit

When a rooftop PV system in Canton Bern is permit-free, when only the eBau notification procedure applies, and which heritage and K-object exceptions trigger a building permit.

Regional service

Solar Installation Graubünden – Planning to Commissioning

In Canton Graubünden, alpine PV systems deliver up to 50% of annual production in winter – strategically decisive for Swiss supply security. The federal government subsidises large alpine systems with up to 60% of investment costs (for winter yield ≥500 kWh/kW/year). Repower coordinates grid connection and permits regionally. Projects like Nalpsolar (10 MW) and the Axpo expansion in Ilanz (30–50 MW) demonstrate scalability.

Guide

Building permit for PV in Canton Zurich: notification procedure, deadline, exceptions

Find out why most PV projects in Canton Zurich have only needed a notification to the municipality rather than a formal permit since 1 January 2023, which 30-day deadline applies and which exceptions such as core zones or monument protection must be clarified early.

Service

PV Installation

Mounting structure per SIA 261, documented penetrations, SUVA-compliant fall protection and complete handover including string diagram, measurement protocol and photo documentation.