PV export limit in Zug: WWZ 70% rule

For the PV export limit in Zug, the following has applied in the WWZ grid area since 1 January 2026: new systems must be planned so that no more than 70% of their DC module capacity is exported to the grid. The requirement also applies to an existing system when its inverter is replaced. It limits export to the grid, not consumption in the building or charging a battery in between. WWZ identifies configuration in the inverter or energy-management system (EMS) as the technical route. This is not a blanket cantonal rule: outside the WWZ grid area, the responsible distribution network operator determines its own process and technical requirements.

What you need to know first.

In the WWZ grid area, new PV systems have had to limit export to no more than 70% of DC module capacity since 1 January 2026; the same applies when an inverter is replaced. The limit applies only to grid export and still allows self-consumption, battery use and controllable loads. Planning should therefore first establish the grid area and then the technical configuration.

Important

As of 2026, the 70% rule in this guide expressly relates to the WWZ grid area, not all of Canton Zug. For existing systems without an inverter replacement, WWZ states that the further timetable is set by the respective grid operator; change the system only in response to a specific technical requirement.

What determines the right path.

The grid area determines whether the rule applies. The WWZ requirement applies in its own grid area from 1 January 2026, not automatically to every address in Canton Zug; the responsible distribution network operator must therefore be confirmed before detailed planning.

DC module capacity is the decisive value. WWZ limits export capacity to 70% of the modules’ DC rated capacity; a larger module area is not prohibited, but the export peak must be handled separately in the design.

An inverter replacement is a specific trigger. WWZ also applies the 70% rule to existing systems when a new inverter is installed; for a refurbishment, configuration must therefore be included in the technical quotation.

The limit is intended to reduce midday peaks, not prevent solar use in the building. WWZ identifies the inverter and EMS as implementation points; self-consumption through a heat pump, boiler, wallbox or battery remains possible and belongs in load planning.

WWZ quantifies the possible yield reduction. For export limited to 70%, WWZ gives a maximum of 3% of annual yield; that figure concerns curtailment, not the project’s overall economics.

Existing systems without an inverter replacement are not automatic cases. WWZ explains that further implementation and timing for existing systems are set by the respective grid operators; an existing system should therefore not be reconfigured pre-emptively without a specific request.

How the project stays cleanly managed.

  1. 1

    Confirm the grid areabefore sizing anything, check whether the property is in the WWZ grid area. At an address outside that area, the requirements of the local distribution network operator apply, not the WWZ 70% rule automatically.

  2. 2

    Classify the system casenew PV systems and existing systems with an inverter replacement fall within the WWZ case described since 1 January 2026. Record the replacement not merely as service work, but as a design change.

  3. 3

    Separate capacity valuesshow the modules’ DC rated capacity and export capacity limited to 70% distinctly in the diagram, quotation and documents for the grid process.

  4. 4

    Choose the implementationdecide with the electrical contractor whether the limit is configured in the inverter or the EMS. The chosen solution must reliably keep the export limit without unnecessarily blocking self-consumption.

  5. 5

    Include loadscapture the heat pump, boiler, wallbox and battery storage in the EMS concept. These loads are not the export limit itself, but can use PV electricity in the building when grid export reaches its 70% boundary.

  6. 6

    Document the configuration and verify it before commissioningcompare the limit set in the inverter or EMS with the modules actually installed. Repeat the same check for any later inverter replacement.

Questions to settle before the quote.

  • Before requesting a quote, determine whether the property is in the WWZ grid area and the 70% requirement therefore applies
  • Show DC module capacity and permitted export capacity separately in the technical concept
  • Specify an inverter or EMS that can demonstrably be configured for the limit
  • Treat an existing system with an inverter replacement as a new planning case

Common questions on this topic.

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Zug, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

Solar Installation Zug – Planning to Commissioning

In Zug, tech companies and blockchain firms drive demand for renewable energy – often as part of measurable ESG goals. WWZ provides administrative support for ZEV/LEG models. From 2026, LEG enables cross-property electricity communities with network fee reduction. This requires project management that integrates metering concept, storage logic and community model from the start.

Guide

Grid Operator Registration PV Bern: BKW & ewb Process

In canton Bern the responsible grid operator depends on the location: ewb in the city of Bern, BKW across most of the rest of the canton, plus local utilities such as Localnet (Burgdorf). The contractor submits a technical connection application (TAG) before construction; building is only permitted after approval.

Regional service

Solar system Zug – Storage & wallbox integrated

In Zug, usage profile, charging power, grid connection and future expansion matter more than generic battery recommendations.

Guide

What to consider for a PV system? The Swiss guide before your first quote

The key points before buying a photovoltaic system – roof, electricity use, system size, components, costs, incentives and permits – in the order that actually matters.

Regional service

PV Installation Zug – Roof & Electrical

Canton Zug combines high innovation density with a strong sustainability agenda. WWZ (Werke Zug) has remunerated feed-in at around 8.5 Rp./kWh since July 2025; from 2026 remuneration tracks the BFE reference market price (quarterly, statutory minimum 6 Rp./kWh up to 30 kW) plus HKN. Many companies in Crypto Valley use solar systems as part of their ESG strategy – and expect installation quality matching international headquarters standards. Compact geography and high building density make ZEV and LEG models particularly economical.

Guide

Basel-Stadt solar offensive: what owners should clarify before PV planning

Understand what Basel-Stadt’s solar offensive means for owners: suitable roof areas, protected buildings, notification path, incentives, IWB connection and project timing.