Skip to content
GuideEconomicsLuzern

LEG in Lucerne: Sharing Solar Power Locally

A LEG in Lucerne allows solar power to be shared between several properties when participants are connected in the same municipality, the same distribution grid area and at the same voltage level. In the standard case, this means the City of Lucerne in the ewl area; elsewhere in the canton, the responsible grid operator, such as CKW, determines the grid topology and registration route. The community’s production capacity must reach at least 5% of the combined connection capacity of all participating end consumers, and every connection needs a smart meter. ewl states that a missing smart meter and the formation of a LEG take at least 3 months. A PV system alone does not create a LEG: roles, agreement, metering and billing must be clarified before registration.

What is a LEG in Lucerne?

Since 1 January 2026, a local electricity community (LEG) in Canton Lucerne can share solar power through the public distribution grid within the same political municipality. The requirements are the same grid operator and voltage level, production capacity of at least 5% of consumers’ connection capacity, and smart meters. ewl and CKW check the specific grid topology.

Important

As of 29 August 2026, “LEG in Lucerne” is not one uniform cantonal grid process: ewl is responsible for the City of Lucerne, while CKW or another utility may be responsible elsewhere depending on the address. The 5% threshold alone is not sufficient; municipality, grid area, voltage level, smart meters and the responsible operator’s review must also be satisfied.

Key figures: LEG solar power Lucerne

Key figures for LEG solar power Lucerne, updated 29 August 2026
MetricValue
LEG availablesince 1 January 2026
Local scopesame municipality, grid area and voltage level
Production ratioat least 5% of end consumers’ connection capacity
Meteringsmart meter for every connection
ewl timingformation no earlier than within 3 months

What determines the right path.

The grid operator and municipal boundary come first. Art. 17d StromVG enables LEG throughout Switzerland, but ewl and CKW determine the concrete grid topology in their own supply areas. An address in the City of Lucerne is therefore checked differently from a property in the CKW area outside the city; a canton-wide LEG cannot be assumed.

The 5% rule refers to connection capacity, not roof area. ewl gives the example of 100 kW of combined connection capacity requiring at least 5 kWp of installed PV capacity. Adding further consumption sites increases the reference value, so production capacity must be recalculated under Art. 19e StromVV.

Smart meters are a prerequisite for metering. When a membership application is submitted, ewl installs a missing smart meter free of charge within 3 months; the same metering requirement belongs in the initial check for a CKW LEG. Without meter data, solar production, consumption and LEG electricity cannot be billed correctly.

LEG, ZEV and vZEV require different planning decisions. The January 2026 SFOE overview describes a LEG as using the public distribution grid; ZEV and vZEV rely on different connection and metering concepts. Simply treating an existing self-consumption arrangement as a LEG can lead to the wrong topology or billing model.

The internal agreement must exist before the application. Art. 19f StromVV requires written rules covering, among other things, representation, remuneration for locally generated electricity, administration and billing, and entry and exit. CKW refers to LEGHub for registration and administration; in the ewl area, formation also uses the LEGhub process.

Economics depend on more than the feed-in tariff. The SFOE overview states that the LEG or its representative sets the terms for internal electricity distribution; ewl identifies lower electricity costs and higher revenues as possible effects. Solar-power pricing, residual supply, grid use and billing therefore need to be modelled together.

How the project stays cleanly managed.

  1. 1

    Check the supply area and topologyfirst identify the responsible distribution grid operator for every interested address. In the City of Lucerne, ewl is the relevant contact; elsewhere, CKW or another utility may be responsible depending on the location. The municipality and voltage level must fit the LEG requirements together.

  2. 2

    Record participants and roleslist PV producers, electricity-only consumers and any storage operators by name. Art. 17d StromVG permits these roles in a LEG; the allocation determines which production and consumption data later enter the billing model.

  3. 3

    Calculate the production ratiocompare installed PV production capacity with the combined connection capacity of all participating end consumers. With 100 kW of connection capacity, the ewl example requires at least 5 kWp of PV capacity; Art. 19e StromVV is the governing reference for the 5% check.

  4. 4

    Prepare meteringdocument the smart-meter status of every connection and initiate installation with the responsible grid operator. ewl states that a missing device is installed free of charge within 3 months; with CKW, the applicable process and dates must be confirmed before registration.

  5. 5

    Define the agreement and billingprepare the written agreement under Art. 19f StromVV before filing. It should set out representation, the internal solar-power price, data-processing and billing costs, entry and exit, and the treatment of residual supply and surpluses; LEGHub and ewl provide the practical process for this.

  6. 6

    Register the LEG with the grid operator and link the PV projectsubmit the formation or registration request with addresses, technical system data and the representative. ewl creates the LEG for the requested date, no earlier than within 3 months; CKW uses LEGHub for registration. Only then should PV sizing, storage options and internal price assumptions be fixed as one economic model.

Questions to settle before the quote.

  • ewl, CKW or another distribution grid operator: match the municipality and voltage level of every address
  • Calculate the 5% minimum capacity against the total connection capacity of participating consumption sites
  • Define smart meters, the LEG agreement under Art. 19f StromVV and internal billing before registration
  • Distinguish ewl’s formation process, with the earliest start within 3 months, from registration with CKW

More questions: LEG solar power Lucerne

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Luzern, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

Solar Installation Luzern – Planning to Commissioning

Lucerne is one of the few cantons requiring solar systems even for comprehensive roof renovations – an extended obligation beyond the pure new-build mandate. From 2026 feed-in is remunerated on a market basis (SFOE reference market price, statutory minimum 6 Rp./kWh up to 30 kW plus HKN) and CKW offers dynamic tariffs that better reward self-consumption. For project management, this means metering concept and storage sizing must be designed for flexible tariff structures during the planning phase.

Guide

Assessing PV economics in Canton Zug correctly

Assess which factors genuinely drive PV system economics in Canton Zug, from self-consumption and current WWZ tariffs to ZEV models, LEG and Pronovo one-time payment.

Regional service

PV Installation Luzern – Roof & Electrical

In Canton Lucerne, CKW (Axpo subsidiary) serves the entire grid area; from 2026 the feed-in is based on the quarterly SFOE reference market price, with a statutory minimum of 6 Rp./kWh up to 30 kW plus a guarantee-of-origin (HKN) payment. Lucerne fully implemented MuKEn 2014 and requires solar systems even for major roof renovations – not only new builds. The mild climate around Lake Lucerne reduces module temperature losses, while Central Switzerland strategically uses solar power to relieve winter electricity grids.

Guide

Self-consumption, vZEV and LEG in Schaffhausen: using solar power correctly

Assess when self-consumption, vZEV or LEG make sense in Schaffhausen: check metering model, grid connection, storage, tenant electricity and Pronovo separately.

Service

Solar system installation

From the initial estimate and 3D survey through a transparent quote to full commissioning — one project, one process, one contact.

Guide

vZEV and local electricity communities: planning PV self-consumption in Schaffhausen

Assess when ZEV, virtual ZEV or local electricity community makes sense for PV in Schaffhausen: prepare metering concept, grid operator, participants, storage and billing cleanly.