PV feed-in payment Valais: EnBAG rates 2026

In the EnBAG grid area, PV feed-in payment in Valais in 2026 is 14.00 ct./kWh from April to September and 6.5 ct./kWh from October to March for systems below 80 kVA, excluding VAT. Owners who transfer guarantees of origin to EnBAG through a Pronovo standing order and also supply the physical energy to EnBAG receive an additional 1.5 ct./kWh. The voluntary TOP-40 model limits export power at the connection point to no more than 60% of installed DC capacity and increases the EnBAG feed-in rate for all exported energy by 8%. These values do not automatically apply across the canton: the responsible distribution system operator must first be confirmed for each property. Where no remuneration agreement exists, the quarterly BFE reference market price and federal minimum payments form the fallback framework.

How high is PV feed-in payment in Valais in 2026?

In the EnBAG grid area, different summer and winter rates apply in 2026 to systems below 80 kVA. HKNs and TOP-40 can add remuneration but require separate contracts and technical conditions. For other Valais grid areas, check the local operator; federal values are only the fallback where no agreement exists.

Important

As of 27 August 2026, the published EnBAG rates apply only in the EnBAG grid area and to systems below 80 kVA. The Q2 2026 BFE reference market price of 3.896 ct./kWh is a fallback where no agreement exists, not a replacement for an existing EnBAG contract. Confirm rates, HKNs and the marketing model with the responsible grid operator before ordering.

Key figures: PV feed-in payment Valais

Key figures for PV feed-in payment Valais, updated 27 August 2026
MetricValue
EnBAG summer14.00 ct./kWh from April to September, excluding VAT
EnBAG winter6.5 ct./kWh from October to March, excluding VAT
Guarantee of originAdditional 1.5 ct./kWh when transferred to EnBAG
TOP-408% rate bonus with no more than 60% DC export power

What determines the right path.

The grid operator determines the actual rate. EnBAG accepts surplus energy only from systems in its own grid area; a Valais address outside that area needs the terms of its responsible distribution system operator.

Capacity and season determine the EnBAG standard rate. The 2026 price sheet applies to systems below 80 kVA and states 14.00 ct./kWh for April to September and 6.5 ct./kWh for October to March, excluding 8.1% VAT. EnBAG handles systems from 80 kVA individually.

The federal value is not a second EnBAG rate. Without a remuneration agreement, the quarterly BFE reference market price has served as the fallback since 2026. For photovoltaics it was 10.266 ct./kWh in Q1 and 3.896 ct./kWh in Q2; capacity- and self-consumption-dependent minimum rules also apply up to 150 kW.

Guarantees of origin must be separated from physical energy. EnBAG states an additional 1.5 ct./kWh if the energy is supplied to EnBAG, the system is certified and HKN transfer is set up through a standing order in the Pronovo system.

TOP-40 is a voluntary model with a technical commitment. Maximum export power is limited to 60% of installed DC capacity; in return, EnBAG increases the applicable rate for all exported energy by 8%. Profitability depends on orientation, self-consumption and the load profile.

Only electricity actually exported counts toward feed-in revenue. A robust calculation separates annual production, self-consumption, storage flows, summer and winter exports and HKN revenue, and also tests a quarter with a low market price.

How the project stays cleanly managed.

  1. 1

    Confirm the grid areaidentify the distribution system operator from the connection address. Use the values stated here only for an EnBAG connection; otherwise request the current price sheet from the local operator.

  2. 2

    Define the system and metering conceptrecord AC apparent power in kVA, installed DC capacity, summer and winter production, self-consumption and storage flows separately. From 80 kVA, an individual EnBAG assessment is required.

  3. 3

    Compare the standard rate and TOP-40model exported kWh by season. Under TOP-40, apply the 8% bonus only to actual exports and simulate potential losses from the 60% power limit.

  4. 4

    Register and certify the systemregister the grid connection and generating system according to EnBAG requirements. After commissioning, complete certification for the Pronovo HKN system.

  5. 5

    Set up HKN transferrecord the standing order in the Pronovo system in favour of EnBAG and also supply the physical energy to EnBAG. When switching to third parties, observe the EnBAG notice period of 30 days to the end of a quarter.

  6. 6

    Check settlementreview summer and winter exports, the HKN item and any TOP-40 bonus separately. If contract terms change, update the profitability calculation instead of carrying one rate across the entire system life.

Questions to settle before the quote.

  • Check the responsible distribution system operator because the EnBAG rate does not apply across the canton
  • Classify 14.00 ct./kWh in summer and 6.5 ct./kWh in winter for EnBAG systems below 80 kVA
  • Secure the HKN add-on of 1.5 ct./kWh through Pronovo certification and a standing order
  • Compare TOP-40 with its 60% export cap and 8% bonus against the standard rate

More questions: PV feed-in payment Valais

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Wallis, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

Solar Installation Wallis – Planning to Commissioning

In Valais, major projects like Grands Plans (Alpiq, 10.5 MWp, 2,450 m) and Belalp (IWB, 12 GWh/year, 2,600–2,700 m) drive alpine solar expansion. The federal government subsidises alpine systems with up to 60% of investment costs. The Belalp municipal referendum (November 2024: double yes) shows: transparent project management and community involvement are the key to realisation in the Valais Alps.

Guide

Assessing PV economics in Canton Zug correctly

Assess which factors genuinely drive PV system economics in Canton Zug, from self-consumption and current WWZ tariffs to ZEV models, LEG and Pronovo one-time payment.

Regional service

PV Installation Wallis – Roof & Electrical

Valais has the highest solar irradiation in Switzerland – Sion counts over 2,100 sunshine hours per year. EW Obergoms and EnBAG remunerate feed-in from 2026 at the BFE reference market price (statutory minimum 6 Rp./kWh up to 30 kW) plus guarantees of origin (HKN). Alpine systems deliver 40–50% of annual production in winter – strategically decisive for national supply security. Extreme conditions (wind, snow, UV) require mounting structures and installation details that exceed lowland standards.

Guide

Self-consumption, vZEV and LEG in Schaffhausen: using solar power correctly

Assess when self-consumption, vZEV or LEG make sense in Schaffhausen: check metering model, grid connection, storage, tenant electricity and Pronovo separately.

Service

Solar system installation

From the initial estimate and 3D survey through a transparent quote to full commissioning — one project, one process, one contact.

Guide

vZEV and local electricity communities: planning PV self-consumption in Schaffhausen

Assess when ZEV, virtual ZEV or local electricity community makes sense for PV in Schaffhausen: prepare metering concept, grid operator, participants, storage and billing cleanly.