SAK PV export limitation Appenzell I.Rh.: 70%

For PV export limitation in the SAK grid area of Appenzell Innerrhoden, SAK sets the maximum export at the house connection to 70% of installed DC panel capacity. This standard applies to systems whose technical connection application is assessed from 1 January 2026, as well as to newly installed inverters and existing systems that are extended or renewed. The limit can be implemented through a fixed inverter setting or an energy-management system; if the energy management fails, the maximum export capacity must still not be exceeded. If the registered export capacity requires grid reinforcement, SAK may specify a lower temporary limit until that work is complete. The module layout, inverter and technical connection application must therefore be treated as one grid-planning decision.

Does the 70% export limit apply to every PV system in Appenzell Innerrhoden?

In the SAK grid area, a newly assessed or technically modified PV system is generally limited to 70% of installed DC module capacity at the house connection. For owners in Appenzell Innerrhoden, the decision therefore depends not only on module area but also on inverter settings, fail-safe energy management and SAK’s technical connection application.

Important

As of 31 July 2026, the 70% rule is a SAK requirement for its grid area, not a canton-wide identical rule for every address in Appenzell Innerrhoden. It limits export at the house connection; where grid reinforcement is needed, SAK may additionally set a lower temporary export capacity until completion.

Key figures: PV export limitation AI

Key figures for PV export limitation AI, updated 31 July 2026
MetricValue
Standard limit70% of installed DC panel capacity
TriggersTAG from 1 January 2026 or technical modification
Grid-supportive curtailmentup to 3% of annual energy
SAK implementationfixed inverter setting or fail-safe EMS
Grid reinforcementcan take from 2 months to several years

What determines the right path.

The trigger date is specific: SAK’s requirement applies to systems whose technical connection application has been assessed from 1 January 2026. A quote that does not establish this TAG status can therefore miss the required inverter or EMS setting.

The 70% requirement relates to DC panel capacity and the house connection, not to an arbitrarily chosen AC inverter rating. The SAK layout must therefore state installed module capacity clearly so maximum export can be parameterised correctly.

The technology choice has a fixed safety condition: SAK permits either a fixed inverter limitation or an energy-management system. If the EMS fails, the specified maximum export capacity must not be exceeded; a control value planned only in software is insufficient without a fail-safe concept.

For existing systems, the limit is not only a new-build issue. SAK names newly installed inverters as well as extensions or renewals; the limit then applies to the entire system behind the same metering circuit or to all metering circuits within a cumulative measurement.

Grid-supportive use is limited, but not unlimited: SAK’s technical conditions permit curtailment at the connection point of up to 3% of annually generated energy for grid-supportive flexibility use without the producer’s consent and without compensation. Above 1,200 metres above sea level, a lower limit may be required where the 70% limit demonstrably curtails more than 3% of annual energy.

The desired export capacity can change the schedule: if the house connection is too small, SAK must reinforce the service line and/or upstream grid. The grid-connection customer bears the service-line reinforcement, while SAK finances the upstream grid; until completion, which SAK says can take from two months to several years, a lower export capacity may apply.

How the project stays cleanly managed.

  1. 1

    Set system size and operating objective before the TAGdetermine module capacity, self-consumption, grid export and the remuneration model with the system supplier. SAK links this choice to the metering arrangement and does not assess it only after installation.

  2. 2

    Submit the technical connection application to SAKthe TAG is completed through ElektroForm online and assessed by SAK. For the 70% rule, record whether assessment is from 1 January 2026 or whether an existing system is technically modified.

  3. 3

    Define the export limit in the execution diagramthe electrical installer files the installation notice with execution diagram and defined metering arrangement with SAK. The 70% limit at the house connection and the selected inverter or EMS solution belong together there.

  4. 4

    Decide on grid reinforcement before orderingif the grid connection is insufficient for the registered export capacity, SAK requires an installation notice, an assessed connection application and a signed grid-connection agreement. Plan for a lower export capacity until reinforcement is completed.

  5. 5

    Parameterise and build the system in line with the TAGcontractors carry out the installation according to SAK’s assessment, permits and technical rules. With EMS control, the fault case must also ensure that the maximum permitted export is not exceeded.

  6. 6

    Complete metering, test record and safety certificateafter installation work, the electrical installer orders the energy meter from SAK. For commissioning, the owner and system supplier confirm in the test record that settings comply with SAK’s technical conditions; the safety certificates are sent to SAK.

Questions to settle before the quote.

  • Check whether the technical connection application is assessed from 1 January 2026 or whether an inverter is replaced, extended or renewed
  • Include 70% of the installed DC module capacity at the house connection in the inverter or EMS design
  • For an EMS solution, define the safe state in the event of failure: the maximum export capacity must not be exceeded then either
  • Clarify with SAK before installation whether grid reinforcement is needed and whether a lower limit applies until it is completed

More questions: PV export limitation AI

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Appenzell Innerrhoden, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

Solar Installation Appenzell Innerrhoden – Planning to Commissioning

In Canton Appenzell Innerrhoden, agricultural buildings – barns with large south-facing roof areas – are at the centre of solar development. EWA handles grid connection regionally. The canton offers good irradiation values despite its alpine location. Dual use (agri-PV) enables farmers an additional income stream without competing for farmland.

Guide

Grid Operator Registration PV Bern: BKW & ewb Process

In canton Bern the responsible grid operator depends on the location: ewb in the city of Bern, BKW across most of the rest of the canton, plus local utilities such as Localnet (Burgdorf). The contractor submits a technical connection application (TAG) before construction; building is only permitted after approval.

Regional service

PV Installation Appenzell Innerrhoden – Roof & Electrical

Appenzell Innerrhoden has a high density of agricultural PV systems on barns and farm buildings. EWA (Elektrizitätswerk Appenzell) compensates from 6 Rp./kWh. For landscape-compatible rooftop systems in building and agricultural zones, a notification procedure replaces the building permit. The canton's pragmatic energy policy – shaped by the Landsgemeinde tradition – treats solar as a natural part of the landscape.

Guide

What to consider for a PV system? The Swiss guide before your first quote

The key points before buying a photovoltaic system – roof, electricity use, system size, components, costs, incentives and permits – in the order that actually matters.

Service

Solar system installation

From the initial estimate and 3D survey through a transparent quote to full commissioning — one project, one process, one contact.

Guide

Basel-Stadt solar offensive: what owners should clarify before PV planning

Understand what Basel-Stadt’s solar offensive means for owners: suitable roof areas, protected buildings, notification path, incentives, IWB connection and project timing.