Notifying a solar system in Schwyz: 20 days before work

Canton Schwyz has three building permit procedures — the ordinary, the simplified and the notification procedure. For solar installations the third is normally decisive, but only if two sets of requirements are met cumulatively. On location: the notification procedure applies to roof-mounted systems in building and agricultural zones, including the roofs of annexes or ancillary buildings such as garages and carports, and to roof and facade systems in industrial and commercial zones and in zones for public buildings and facilities. In the latter zones the mere duty to notify applies even where the system does not meet the design criteria. On design: on a pitched roof a system counts as "sufficiently adapted" if it projects at most 20 centimetres perpendicular to the roof surface, does not extend beyond the roof surface when seen from above, is low-reflection according to the state of the art, and is arranged compactly. Alternative criteria apply to flat roofs: at most one metre above the upper edge of the roof rim, set back far enough from the roof edge that the system is not visible from below at a 45 degree angle, and likewise low-reflection. If both sets are met, the notification is filed online via the eBau portal as a "building notification for a minor project", at least 20 days before work starts. Absent any contrary reply, work may begin once that period has elapsed. The cantonal planning guide expressly clears up a common misconception: solar systems that are merely subject to notification are still subject to a building permit requirement — the notification procedure is a permit procedure, not a waiver of one.

Is my solar installation in Canton Schwyz exempt from a permit if it is only subject to notification?

Procedural guidance for owners in Canton Schwyz who want to know whether their planned solar installation runs through the notification procedure, which documents are required, when work may begin, and in which cases the installation falls into the simplified or ordinary procedure instead.

Important

The cantonal planning guide expressly states that solar installations subject only to notification are nevertheless subject to a building permit requirement. The duty to notify also does not exempt the project from other requirements, in particular not from the fire safety permit. It is recommended to inform neighbours about the project in advance, regardless of which procedure applies, and — especially for larger systems — to clarify technical feasibility with the local energy supplier at an early stage. Where a potentially problematic glare situation exists, the planning guide recommends a glare assessment. This page provides technical orientation and replaces neither advice from the competent municipal building authority nor legal advice.

Key figures: PV permits Schwyz

Key figures for PV permits Schwyz, updated 02 August 2026
MetricValue
Standard procedureNotification as a "building notification for a minor project"
DeadlineAt least 20 days before work starts
FilingOnline via the canton's eBau portal
Pitched roofMax. 20 cm construction height, no overhang, low-reflection, compact
Flat roofMax. 1 m above the roof rim, not visible from below at 45°
Notification and permitSystems subject to notification remain subject to a permit
New buildsSelf-generation obligation: min. 10 W/m² ERA, max. 30 kW

What determines the right path.

Location and design must both fit: if the system meets both sets of criteria, the notification procedure applies. If not, it must be authorised through the simplified or ordinary procedure.

Industrial and commercial zones and zones for public buildings and facilities enjoy a relaxation: there, roof and facade systems are subject only to notification even if they do not count as sufficiently adapted.

Protected objects change the procedure fundamentally: for cultural and natural monuments of national or regional importance, ISOS-A townscapes and buildings in the cantonal protection inventory, the notification procedure does not apply. Only in BLN areas does it remain possible if heightened requirements are met.

The notification does not replace the fire safety permit: solar installations require a fire safety permit and must comply with current fire safety regulations. A fire brigade plan must be submitted with the notification, among other documents.

For new builds a substantive permit condition is added: since 1 May 2022 all (replacement) new builds are subject to the self-generation obligation. To be eligible for a permit, all (replacement) new builds within the green area of the cantonal map must meet it.

Additional cantonal or municipal design criteria may only be applied if they do not restrict the use of solar energy more than federal law does and are proportionate to safeguarding legitimate protection interests.

How the project stays cleanly managed.

  1. 1

    Use the cantonal geoinformation system to check whether the planned system lies in a protection zone or on a protected object. The impact of the new system must also be assessed in the immediate vicinity of protected objects.

  2. 2

    Work through and document the design criteria for the pitched or flat roof on the specific project: construction height, overhang, set-back, low reflectivity and compact arrangement.

  3. 3

    For new builds, clarify the self-generation obligationunder § 8c of the cantonal energy act new builds must generate part of the electricity they need themselves; § 24d of the cantonal energy ordinance requires at least 10 W per m² of energy reference area, with no more than 30 kW required in total.

  4. 4

    File the notification online via the eBau portal as a "building notification for a minor project" at least 20 days before work starts, with complete documents: site plan including fire brigade plan, roof plan with dimensioned roof and roof-edge distances, roof section with construction height, and technical specifications.

  5. 5

    Wait out the notification period. Absent any contrary reply, work may begin once the 20 days from receipt of the notification by the competent authority have elapsed. If the authority concludes that an ordinary or simplified procedure is required, it says so in writing within the notification period and refers the application to that procedure.

Questions to settle before the quote.

  • Notification at least 20 days before work starts via eBau as a "building notification for a minor project"
  • Check the location and design criteria cumulatively before relying on the notification procedure
  • Protected objects, ISOS-A townscapes and the cantonal protection inventory lead to the ordinary procedure
  • The self-generation obligation for new builds as a precondition of obtaining a permit

More questions: PV permits Schwyz

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Schwyz, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

PV Installation Schwyz – Roof & Electrical

Schwyz is seeing strong growth in private PV systems, especially in the growing agglomeration around Lake Zurich and the March district. From 2026, EWS AG remunerates surplus energy at the BFE reference market price (around 7 Rp./kWh, set quarterly) plus around 2.5 Rp./kWh for guarantees of origin (HKN); the statutory minimum is 6 Rp./kWh up to 30 kW. In the Schwyz high valley, systems deliver significantly more winter electricity thanks to altitude – installation quality must withstand alpine wind loads and snow conditions.

Guide

Solar Permit Bern: Notification Instead of Building Permit

When a rooftop PV system in Canton Bern is permit-free, when only the eBau notification procedure applies, and which heritage and K-object exceptions trigger a building permit.

Regional service

Solar Installation Schwyz – Planning to Commissioning

Canton Schwyz is growing – especially around Lake Zurich and in the March district. From 2026, EWS AG (Axpo subsidiary) compensates feed-in at the BFE reference market price (around 7 Rp./kWh, set quarterly) plus around 2.5 Rp./kWh for guarantees of origin (HKN) – statutory minimum 6 Rp./kWh up to 30 kW – and supports alpine solar projects. The failed referendum on the Alpin Solar Ybrig project (2024) shows: community engagement and transparent communication are as decisive in Schwyz as technical excellence.

Guide

Building permit for PV in Canton Zurich: notification procedure, deadline, exceptions

Find out why most PV projects in Canton Zurich have only needed a notification to the municipality rather than a formal permit since 1 January 2023, which 30-day deadline applies and which exceptions such as core zones or monument protection must be clarified early.

Service

PV Installation

Mounting structure per SIA 261, documented penetrations, SUVA-compliant fall protection and complete handover including string diagram, measurement protocol and photo documentation.