Skip to content
GuideFundingFreiburg

PV ZEV Incentive in Canton Fribourg

The PV incentive for a ZEV in the Canton of Fribourg is CHF 750 per new self-consumption association when the requirements of the cantonal Energy Office are met. In the standard case, an additional electricity meter is installed, at least one existing building is included and PV capacity reaches at least 10% of the association’s total connection capacity. The grid connection must be validated by the distribution network operator, followed by an NIV safety certificate. The application must reach the Energy Office before construction starts, not after installation or purchase. As of 1 June 2026, the measure runs until 31 December 2026 or until the CHF 100,000 budget is exhausted.

How much is the PV incentive for a ZEV in the Canton of Fribourg?

In the Canton of Fribourg, new ZEVs and similar models can receive CHF 750 if they provide an additional meter, include an existing building and reach PV capacity of at least 10% of total connection capacity. The application must reach the Energy Office before construction; the measure ends on 31 December 2026 or when CHF 100,000 is exhausted.

Important

The key limit is the start date: under the Fribourg Energy Office and Article 24 of the Subsidies Act, no grant is available for work already under way or purchases already made. The measure may also end before 31 December 2026 if the CHF 100,000 is exhausted. Confirm the current budget and eligibility of a similar model with the Energy Office before ordering.

Key figures: Self-consumption association incentive Fribourg

Key figures for Self-consumption association incentive Fribourg, updated 10 August 2026
MetricValue
Grant amountCHF 750 per new self-consumption association
Minimum capacityPV capacity of at least 10% of total connection capacity
Application timingApplication must reach the Energy Office before construction starts
Programme periodUntil 31 December 2026 or until CHF 100,000 is exhausted
Required evidenceAdditional meter, existing building, grid validation and NIV safety certificate

What determines the right path.

The model must be new and connect several consumers. Article 54c of Fribourg’s Energy Ordinance RSF 770.11 covers a new self-consumption association or a similar model; at least one existing building must be included. A standalone PV system without a new association therefore does not automatically meet the published criteria.

The 10% threshold refers to the association’s total connection capacity. The PV system or combined systems must reach at least 10% of that capacity. This figure belongs in the metering and connection concept before quoting, because the module area of one roof alone is not the decisive reference.

The additional electricity meter is a separate funding requirement. The application documents also require a diagram of the system and association showing the meters. Meter space, the metering concept and responsibility for internal billing should therefore be clarified with the electricity supplier and distribution network operator before construction.

The grid connection must receive technical confirmation. The Energy Office requires the connection to the distribution grid to be validated by the distribution network operator. The system must also be inspected and released for operation with a safety certificate under the NIV; these documents are more than mere funding paperwork.

Timing determines eligibility. Under Article 24 of the Subsidies Act of 17 November 1999, no grants are awarded for work already under way or purchases already made. The application must therefore have reached the Energy Office before construction starts; work should begin only after the funding commitment.

The grant is flat-rate and time-limited. Fribourg’s measure pays CHF 750 per new self-consumption association, not a percentage of the PV investment. It applies until 31 December 2026 or until the allocated CHF 100,000 is exhausted; the remaining budget cannot be inferred from this article before applying.

How the project stays cleanly managed.

  1. 1

    Define the associationrecord which consumers will participate, which existing building is included and whether a conventional ZEV or a similar model is planned. A standalone system without a new association does not fit this incentive route.

  2. 2

    Request connection and metering data from the electricity supplier: the new association requires the request form, total connection capacity, additional meter and technical connection concept. The distribution network operator must later validate the connection.

  3. 3

    Plan the PV system and association togethersize the system or systems to meet the 10% threshold and create a diagram showing PV, the association and meters. The quote, module plan and metering concept must describe the same project version.

  4. 4

    Submit the application before construction startsunder the Energy Office documents, the signed application form is sent by post, while the other documents should preferably be submitted electronically. Key attachments are the association request form, quote, association diagram and electricity supplier’s decision.

  5. 5

    Wait for the funding commitment before startingafter review, a funding commitment is issued; according to the guidance, work may then begin. Ordering or installing before the application, or before the commitment, increases the funding risk and may exclude the grant.

  6. 6

    Document completionafter installation, provide confirmation that the electricity supplier activated the association or a first invoice to the association, the invoices and the signed completion form. The technical inspection and NIV safety certificate must document release for operation before the Energy Office reviews payment.

Questions to settle before the quote.

  • Relate 10% system capacity to the association’s total connection capacity
  • Document the additional meter, existing building and grid-operator decision
  • Submit the application, quote and association diagram before construction starts
  • Prepare activation evidence, invoices and the completion form for payment

More questions: Self-consumption association incentive Fribourg

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Freiburg, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

Solar Installation Freiburg – Planning to Commissioning

Canton Fribourg is among the roughly ten cantons exceeding MuKEn minimum requirements – with extended energy efficiency standards for all building types. Tax deductibility of installation costs noticeably improves economics. In the Sense-Oberland, pre-alpine southern exposure and moderate altitude (600–1,200 m) deliver consistently good yields.

Guide

Pronovo one-time payment for PV in Canton Bern

How high the Pronovo one-time payment for a PV system in Canton Bern is, how it splits into a base and a capacity payment, when to file the application, and how federal funding, the absence of cantonal PV funding and the tax deduction relate to each other.

Regional service

PV Installation Freiburg – Roof & Electrical

Fribourg bridges German and French-speaking Switzerland – also in energy policy. The main utility is Groupe E (BKW only in a few border areas); from 2026, feed-in follows the BFE reference market price (approx. 10.27 Rp./kWh in Q1 2026) with a guaranteed minimum of 6 Rp./kWh for systems up to 30 kW. The University of Fribourg researches next-generation perovskite solar cells. The canton implemented MuKEn 2014 with extended standards; there is no general cantonal PV funding programme (the 25% / ZEV top-up is a City of Fribourg programme), but installation costs are tax-deductible.

Guide

PV bonus for roof renovation in Canton Zug

When Canton Zug pays a PV bonus during roof or facade refurbishment, which area quota applies and why the funding application must be filed before work starts.

Service

Solar system installation

From the initial estimate and 3D survey through a transparent quote to full commissioning — one project, one process, one contact.

Guide

Photovoltaic incentives in Nidwalden: 2026 rules

Which cantonal support paths for photovoltaics exist in Nidwalden, how solar consultation works and what to check separately through Pronovo.