PV grid connection Aargau: TAG, notice and SiNa process

A PV grid connection in Aargau works when the connection request, installation notice, metering concept and safety certificate are coordinated with the responsible distribution grid operator in the correct order before installation. In AEW’s service area, AEW answers a connection request within three weeks and requires an installation notice submitted by a licensed electrical installer before work begins. For parallel-operated generation systems, the technical connection request (TAG) precedes the installation notice under the works regulations; the notice must follow within six months of TAG approval. Outside AEW’s service area, this process does not apply automatically: the local grid operator’s technical requirements govern. Following the initial electrical test, even a non-grid-connected PV system needs a test record; for a grid-connected system, the installation notice is also required before execution.

What you need to know first.

For a PV system in Aargau, the responsible grid operator must assess the connection and metering concept before implementation. In AEW’s service area, the connection request is answered within three weeks; TAG, the installation notice before work, the initial test and SiNa form the technical process. Other grid areas have their own requirements.

Important

As of 19 July 2026, the three-week response and six-month TAG validity come from the AEW process and works regulations and do not apply automatically to every Aargau connection point. Building-law clearance and binding technical approval remain separate decisions; this is not individual electrical or legal advice.

What determines the right path.

The grid operator depends on the connection point: AEW describes its process only for its own service area. Elsewhere in Aargau, the responsible distribution grid operator decides the connection conditions, metering concept and any required grid upgrade; an AEW approval is not a substitute there.

The technical sequence is binding: for a parallel-operated generation system, the German-speaking Switzerland works regulations require the TAG first and then the installation notice. A TAG expires if no installation notice follows within six months of approval.

The AEW timeframe is a planning anchor, not a construction guarantee: AEW states that it answers a connection request within three weeks. This does not replace a complete technical review or set a date for meter work or any necessary grid reinforcement.

The installation notice belongs before execution: ESTI identifies it as a pre-work notification for PV systems connected to the low-voltage distribution grid. In AEW’s service area, it must be submitted by a licensed electrical installer; a quotation alone is not sufficient.

The metering concept and additional loads determine the modification: AEW checks with the PV registration whether the requested feed-in capacity is available in the grid. Battery storage, a wallbox or heat pump must therefore appear with inverter data and the meter concept in the same technical dossier, not only after installation.

Commissioning must be completed with evidence: ESTI requires an initial test and test record before commissioning, even without a grid connection. For the Pronovo notification, complete certified system data are required after commissioning; integrated systems also need construction or completion photographs.

How the project stays cleanly managed.

  1. 1

    Identify the connection point and grid operatorassign the property to its actual distribution grid operator and clarify whether AEW is responsible. Only then can its three-week response time, portal process and document list be used sensibly as a scheduling basis.

  2. 2

    Set the technical concept before orderingrecord PV capacity, inverter, feed-in capacity, battery storage, wallbox, heat pump and intended self-consumption. In AEW’s service area, the PV registration shows whether the requested feed-in capacity is available in the grid.

  3. 3

    Submit the TAG and await assessmentfor a parallel-operated generation system, the technical connection request is submitted before the installation notice. In AEW’s service area, it goes to the responsible regional centre; according to AEW, the connection request is answered within three weeks.

  4. 4

    File the installation notice through the electrical specialist before work begins: the works regulations require the installation notice before work; in AEW’s service area it must be filed within six months of TAG approval. Use it to align the meter location, metering concept and material scheduling.

  5. 5

    Document installation, testing and the safety certificatebefore commissioning, the electrical specialist performs the initial test and records it in the test record. In the AEW process, the SiNa, PV measurement and test record and commissioning record are relevant documents.

  6. 6

    Complete the grid-side implementation and commissioningdo not commission the system until the agreed grid and metering step has been completed. Keep final system data, test records and grid-operator correspondence together so that connection, acceptance and later Pronovo notification information do not conflict.

  7. 7

    Handle Pronovo after commissioning with the same datasubmit the complete commissioning notification with certified system data. For integrated systems, Pronovo also requires construction or completion photographs; the incentive notification does not replace grid approval.

Questions to settle before the quote.

  • Identify the responsible distribution grid operator and connection point before detailed planning
  • In the AEW service area, file the TAG before the installation notice and before work begins
  • Include battery storage, a wallbox and heat pump in the metering concept rather than after installation
  • Provide the SiNa, measurement and test record and commissioning data for the grid operator and Pronovo

Common questions on this topic.

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Aargau, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

Solar installation in Aarau with Eniwa grid connection

In Aarau, Eniwa AG (formerly IBAarau) is the responsible grid operator for connection, metering and feed-in compensation. What matters here is combining the City of Aarau's communal energy subsidy with the cantonal registration process via the EVEN platform, which we set up correctly for you.

Guide

Grid Operator Registration PV Bern: BKW & ewb Process

In canton Bern the responsible grid operator depends on the location: ewb in the city of Bern, BKW across most of the rest of the canton, plus local utilities such as Localnet (Burgdorf). The contractor submits a technical connection application (TAG) before construction; building is only permitted after approval.

Service

Solar system installation

From the initial estimate and 3D survey through a transparent quote to full commissioning — one project, one process, one contact.

Guide

What to consider for a PV system? The Swiss guide before your first quote

The key points before buying a photovoltaic system – roof, electricity use, system size, components, costs, incentives and permits – in the order that actually matters.

Service

PV Installation

Mounting structure per SIA 261, documented penetrations, SUVA-compliant fall protection and complete handover including string diagram, measurement protocol and photo documentation.