Short answer
Does a rooftop PV system in Canton Bern need a building permit?
In Canton Bern, a sufficiently adapted rooftop PV system usually only needs notification via eBau, at least seven working days before construction starts. A building permit is required if Art. 32a RPV is not met, a K-object is affected or a heritage site of national importance is involved.
Important
As of 2026: permit exemption applies only to sufficiently adapted installations. K-objects (protected and conservation-worthy monuments within a building group) and heritage sites of national importance always require a building permit; conservation-worthy objects without a building group only if the protection interest is affected. The notification procedure also does not release from environmental law and fire protection.
At a glance
Key figures: Solar Permit Bern
| Metric | Value |
|---|---|
| Standard case rooftop | Permit-free, notification only (Art. 18a para. 1 RPG) |
| Notification deadline | At least 7 working days before construction via eBau (Art. 7a BewD) |
| Sufficiently adapted criterion | Max 20 cm clearance, low-reflection, compact (Art. 32a RPV) |
| Permit required | K-objects and heritage sites of national importance (Art. 6 BewD) |
| Entry into force | Revised spatial planning legislation from 1 January 2026 |
Decision points
What determines the right path.
Degree of adaptation: only a sufficiently adapted installation (max 20 cm clearance, no overhang viewed from above, low-reflection, compact per Art. 32a RPV) is permit-free and eligible for the notification procedure.
Heritage status of the property: K-objects (protected and conservation-worthy monuments within a building group) and heritage sites of national importance always require a building permit (Art. 18a para. 3 RPG, Art. 6 BewD).
Conservation-worthy objects without a building group: these are not K-objects; a permit is required only if the protection interest is affected (Art. 7 para. 2 BewD, case-by-case review).
Notification deadline: the notification must reach the host municipality via eBau at least seven working days before construction starts (Art. 7a BewD); too little lead time delays the build.
Substantive law still applies: even under the notification procedure, environmental law and fire protection must be observed; permit exemption does not release from these rules.
Responsible body: in the City of Bern the Building Inspectorate decides, the Office for Environment and Energy (AUE) advises at cantonal level; in case of doubt the regional prefect decides (Art. 48 para. 2 lit. a BewD).
Sequence
How the project stays cleanly managed.
- 1
Check the installationdoes the planned rooftop system meet the Art. 32a RPV criteria (max 20 cm perpendicular clearance, no overhang beyond the roof viewed from above, low-reflection per state of the art, compact)? Only then is it sufficiently adapted.
- 2
Clarify heritage statuscheck whether the property is listed as a K-object or heritage site of national importance in the building inventory; in those cases a building permit is required instead of a notification.
- 3
Pre-clarify in case of doubtif permit exemption is unclear, arrange a preliminary discussion with the heritage office (City of Bern), or the regional prefect decides (Art. 48 para. 2 lit. a BewD).
- 4
Prepare documentsthe notification is created by the building principal or planner via eBau (portal.ebau.apps.be.ch) addressed to the host municipality.
- 5
Meet the deadlinesubmit the notification via eBau at least seven working days before construction starts (Art. 7a BewD).
- 6
Await the decisionthe municipality assesses the installation against the requirements applicable in the notification procedure and communicates the decision via eBau.
- 7
Handle grid connection separatelyarrange the connection with the grid operator (BKW, or Energie Wasser Bern ewb in the City of Bern); this is independent of the notification/permit procedure.
Checklist
Questions to settle before the quote.
- eBau notification: seven working days before construction
- Sufficiently adapted: 20 cm clearance, low-reflection, compact
- Exceptions: K-objects and heritage sites of national importance
- Prepare the BKW or ewb grid connection separately from building law
FAQ
More questions: Solar Permit Bern
Sources
Official sources & references.
The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.
- Information sheet on permit-free solar installations under the notification procedure (Canton of Bern, AUE)Office for Environment and Energy, Canton of Bern
- Energy rules for construction: solar installations and notification procedureEconomic, Energy and Environmental Directorate, Canton of Bern
- Spatial Planning Ordinance (RPV, SR 700.1), Art. 32a permit-free solar installationsFederal Chancellery / Fedlex
- Building Permit Decree of the Canton of Bern (BewD)Canton of Bern / BELEX
- Heureka – Building a roof solar installation (permit guide, Canton of Bern)Canton of Bern (permit guide Heureka)