Skip to content
GuideStorageNeuenburg

Battery storage incentives Neuchâtel: CHF 800 + 80/kWh

Neuchâtel’s battery storage incentive has applied since 1 March 2026 to new stationary batteries at residential buildings where photovoltaic generation is present on the same site and part of the solar electricity is self-consumed. The grant is CHF 800 per installation plus CHF 80 per kWh, capped at 2 kWh of storage per kWp of PV capacity and 50% of the total investment. Vehicle batteries, storage in non-residential buildings, used systems and systems commissioned before 1 March 2026 are excluded; at most one installation per building is supported. The application is submitted to the Service de l’énergie et de l’environnement (SENE) only after commissioning and must arrive no later than 6 months after the OIBT report or commissioning protocol. The minimum capacity needs clarification: the current ASBaSt order says more than 3 kWh, while the SENE website and conditions state 3 kWh.

How much is the battery storage incentive in Neuchâtel?

In Neuchâtel, owners and solar cooperatives can receive CHF 800 plus CHF 80 per kWh for a new stationary PV battery at a residential building. The 2 kWh-per-kWp cap, 50% investment limit and filing within six months of the OIBT report or commissioning protocol apply. The 3 kWh minimum is worded differently in the legal order and SENE documents.

Important

As of 9 August 2026, the current ASBaSt text and the SENE documents differ for exactly 3 kWh. Article 5 para. 1 let. a requires “over 3 kWh”, while the website and general conditions state 3 kWh. A 3 kWh battery should therefore be clarified with SENE in writing before ordering; payment is also limited to available cantonal funds.

Key figures: Battery storage incentives Neuchâtel

Key figures for Battery storage incentives Neuchâtel, updated 09 August 2026
MetricValue
Effective date1 March 2026; earlier commissioning excluded
Grant amountCHF 800 per installation + CHF 80 per kWh
Funding capsMax. 2 kWh/kWp of PV and 50% of total investment
Filing deadlineSix months after the OIBT report or commissioning protocol
Minimum capacityASBaSt: over 3 kWh; SENE documents: 3 kWh – clarify before ordering

What determines the right path.

Building type and location come first. Article 2 ASBaSt limits the incentive to batteries in residential buildings of category I or II under SIA 380/1 in the Canton of Neuchâtel; Article 5 also requires PV at the same site with part of the solar electricity self-consumed. A commercial battery without residential use therefore does not fit this route.

The grant is legally capped. Under Article 4 ASBaSt, it consists of CHF 800 per installation plus CHF 80 per kWh of installed storage; no more than 2 kWh per kWp of PV capacity and no more than 50% of the total investment are eligible. A larger battery may make technical sense, but it does not increase the eligible grant beyond these limits.

The minimum capacity is not currently published consistently. Article 5 para. 1 let. a ASBaSt requires storage capacity “over 3 kWh”, while the SENE website and the general conditions dated 23 February 2026 state a minimum capacity of 3 kWh. A system rated at exactly 3 kWh should therefore be clarified with SENE in writing before ordering.

The incentive is claimed after implementation. General conditions 1.7 and 1.10 require the application after commissioning and set the deadline at no later than 6 months after the date of the OIBT safety report; where no OIBT inspection is required, the commissioning protocol starts the clock. This model does not provide for an award before installation.

The evidence package determines whether the file can be processed. Article 5 ASBaSt and the BaSt form require paid invoices, photographs of the installed battery, proof of PV capacity and the OIBT safety report or, for a DC addition, the commissioning record. If documents are missing, SENE can request supplements and defer processing.

Payment depends on the budget and is not an unconditional entitlement. Under Article 7 ASBaSt, complete applications are handled in order of receipt; general condition 1.20 states that funds are paid only within the available cantonal budget and may be spread across several financial years. The project decision must therefore allow for a budget constraint.

How the project stays cleanly managed.

  1. 1

    Define eligibility before requesting a quotedocument a category I or II residential building under SIA 380/1, a site in the Canton of Neuchâtel, existing or new PV on the same site, partial self-consumption and a new stationary battery. Exclude vehicle batteries, non-residential buildings, used systems and a second installation where one has already been funded.

  2. 2

    Size the battery technically and mark the incentive limits separately: the design should include the load profile, evening and night demand, heat pump, wallbox and PV capacity. In the incentive calculation, enter 2 kWh per kWp of PV and 50% of the total investment as caps; record the “over 3 kWh” wording in Article 5 para. 1 let. a ASBaSt as an open clarification point in the quote.

  3. 3

    Complete installation and commissioning cleanlyconnect the battery to the existing or new PV system and the building installation. Before applying, obtain the OIBT safety report; for a DC addition where no OIBT inspection is required, the commissioning protocol replaces it.

  4. 4

    Assemble the BaSt filecomplete the SENE form, attach the paid invoice and photographs of the battery, document PV capacity with an invoice, Pronovo decision or other evidence, and attach the OIBT report or commissioning protocol. The EGID, storage capacity and commissioning date must match across the form and supporting documents.

  5. 5

    File with SENE on time after commissioningsend the application by email or post to the Service de l’énergie et de l’environnement, and ensure it arrives no later than 6 months after the OIBT report or commissioning protocol. This is a cut-off deadline; under condition 1.10, the entitlement expires after it passes.

  6. 6

    Plan for queries and the budget decisionSENE checks the project and can request missing documents. Under condition 1.9, requested supplements have an initial 3-month period and then a further 3-month period; complete applications are handled by arrival date. Payment follows only after the review and within available funds.

Questions to settle before the quote.

  • Check ASBaSt Articles 2–5: residential building, on-site PV, new stationary battery and the wording “over 3 kWh”
  • Calculate CHF 800 plus CHF 80/kWh with the 2 kWh-per-kWp cap and 50% investment limit
  • Collect the OIBT safety report or commissioning protocol, paid invoice, photographs and PV capacity evidence
  • Submit the application to SENE within six months and clarify the 3 kWh discrepancy in writing before ordering

More questions: Battery storage incentives Neuchâtel

Official sources & references.

The responsible authorities are decisive. Always verify binding details – amounts, deadlines and conditions – for your specific property against the current status of the respective authority.

Continue

Relevant pages for the next step.

For Neuenburg, you'll find matching services, regional projects and related guides that take you forward in practical terms.

Regional service

Solar Installation Neuenburg – Planning to Commissioning

In Canton Neuenburg, defensible quotes, clean project steering and commissioning without loose ends matter most. In the Canton of Neuchâtel, there is no general cantonal PV bonus. The main incentives are Pronovo, the full tax deduction, and the «Programme d'encouragement pour l'énergie», which supports energy renovations. Since 1 March 2026 a cantonal battery-storage contribution applies: a CHF 800 flat rate plus CHF 80 per kWh of storage capacity (max. 50 % of the investment, min. 3 kWh, max. 2 kWh per kW of PV). Viteos, Groupe E, and ENSA offer attractive feed-in tariffs.

Guide

Sizing a PV battery storage system right (Bern)

How big a PV battery storage system in canton Bern should be: sizing rules from Swissolar and SwissEnergy, a guide price of CHF 600-900/kWh, the ewb storage subsidy of CHF 100/kWh limited to the city area, and the duty to report retrofitted storage to Pronovo.

Regional service

PV Installation Neuenburg – Roof & Electrical

In Canton Neuenburg, clean project logic and clear ownership between roof and electrical work matter most. Neuchâtel's utility landscape is mixed: Viteos covers the city and the lake area, Groupe E serves Val-de-Ruz and Val-de-Travers, and ENSA is active in the upper Jura. Feed-in tariffs and ZEV rules therefore differ noticeably by municipality – a per-location check is recommended.

Guide

Battery storage and self-consumption in Zug: when storage, ZEV or vZEV fit a PV system

Assess when battery storage, wallbox, ZEV, vZEV or WWZ self-consumption models in Zug really fit a PV system and when consumption, metering and grid connection need checking first.

Service

Battery & Wallbox

47% of new Swiss PV systems are installed with battery storage today — we show transparently when LFP batteries (CHF 650–1'000/kWh, 15–20 years) pay off and when they do not. Self-consumption rises from 25–35% (PV-only) to 50–65% with battery and EMS.

Guide

Battery storage for PV in Aargau: when storage really makes sense

Assess when a battery storage system fits a PV system in Aargau: prepare self-consumption, AEW metering, grid connection, wallbox, heat pump and incentive logic cleanly.